HW24: Chapter 23

23.6: Figure 23.14 shows the task durations for software project activities. Assume that a serious, unanticipated setback occurs, and instead of taking 10 days, task T5 takes 40 days. Draw up new bar charts showing how the project might be reorganized.

Leave a Reply

Your email address will not be published. Required fields are marked *